If they promise delivery in three years, be suspicious: what the timeline reveals about a developer's finances

"When they promise a pre-sale at three years, be suspicious. It is because the developer does not have the money to finish and depends on sales to build."
— Alejandro Zarfino

There is one figure in every pre-construction contract that buyers tend to read as a calendar detail, when in fact it is an X-ray of the developer's finances: the delivery date.
A seven-story building with 90 apartments can be built, with capital available and a team that knows what it is doing, in a little over a year. If the contract says three years, or four, the question is not why the construction takes so long. The question is where the money to build it is going to come from.
On the Dimes y Billetes podcast, Alejandro Zarfino put it plainly: when a pre-construction project promises delivery in three years, in most cases it is because the developer lacks the resources to finish and needs to sell in order to build. The long timeline is not prudence; it is dependence. Every month that sales fall short of target, construction stops or slows, and the buyer who already paid a deposit becomes the one financing the wait.
The phenomenon is not unique to the Riviera Maya. There are projects in Monterrey that have been stalled for years. Zarfino recalled market research he did in Miami two years ago: 100-story towers with luxury brand names, announced with spectacular renderings, that two years later are still on paper, without ever breaking ground. The mechanism is the same everywhere: pre-sales as a source of financing turn the buyer into an involuntary partner in sales risk.
How, then, should a delivery timeline be read?
Three practical criteria:
Up to 18 months for a mid-rise building is a timeline that indicates construction is funded. It is the technical timeline, not the commercial one.
Between 18 and 24 months remains reasonable for large projects or several simultaneous buildings, as long as construction is visibly underway at the time of signing.
More than 24 months demands an explanation. It does not disqualify the project, but the buyer should ask to see the financing plan or, at minimum, evidence that the developer's previous projects were delivered on the promised date.
The definitive proof, however, is not in the contract but on site. At Distrito Xcalacoco Beach in Playa del Carmen, the first phase of 89 apartments went on sale in July 2025 and homes are being deeded in 2026. The second phase is being built in plain view: a camera points at the construction site and any client can check it. "When you tell a client you are going to put up a seven-story building in a year, they do not believe you," Zarfino said. "We tell them: come back in three months and see for yourself."
A short timeline is not an aggressive sales promise. It is the natural consequence of building with one's own capital. And for the buyer, it is the clearest signal that they will not have to finance someone else's wait.